In accordance with the Program schedule, DCNS is completing equipment integration and harbor acceptance tests on board the first-of-class FREMM multi-mission frigate Aquitaine. All major ship systems must be tested before the major milestone of the first sea going, scheduled next spring.
So far 95% of the electrical and hydraulic equipments of the ship have been installed, so teams are ramping up for the harbor acceptance tests of the principal systems: the information and communication system, the navigation systems (navigation radar, early warning radar), the electric power and distribution system (including four diesel generators), the combat system and the propulsion system.
The first tests of the electric propulsion motors and of the gas turbine started over the last few days and have been successfully completed. For the first time the entire transmission system of the frigate was running, from the motors to the test propellers. This event is an important step, and moving moment, as it represents the first heartbeat of the frigate.
“From now on all our efforts are focused on the preparation of the first sea going scheduled for the spring”, points out Vincent Martinot-Lagarde, DCNS FREMM Program Director.
0 comments:
Post a Comment